IMP#3 tasks to be carried out within the framework of the ITM Task Force

2006-12-19

Task id

Title

Deliverable(s)

Responsible(s) *

Start date
Due date **

Monitoring ***

Status

Reason

PPY

Main Contributors

ITM-05-IMP3-T1-A

Identification of existing equilibrium modules (in conjunction with IMP1).

Documentation of pieces of code in existing transport codes that could be turned into ITM  equilibrium modules.

G. Pereverzev

 

01/07/2005

31/09/2005

 

 

 

 

ITM-05-IMP3-T1-B

Formation of working groups (in conjunction with IMP1).

Creation of functioning working groups

G. Pereverzev

 

01/08/2005

31/12/2005

 

 

 

 

ITM-05-IMP3-T1-C

Preparation of standardised interfaces (in conjunction with IMP1 and ISIP).

Version 1 of the standard interface for each physics module

G. Pereverzev

 

01/08/2006

31/03/2006

 

 

 

 

ITM-05-IMP3-T1-D

Preparation of equilibrium modules by extraction from existing codes (in conjunction with IMP1).

Various equilibrium physics modules that could be used by the CPP or by existing transport codes.

G. Pereverzev

 

01/01/2006

31/12/2006

 

 

 

 

ITM-05-IMP3-T1-E

Implementation of prepared equilibrium modules (in conjunction with IMP1).

Implementation of modules in CPP or existing transport codes (from the above process or from other IMP’s).

G. Pereverzev

 

01/04/2006

31/12/2007

 

 

 

 

ITM-05-IMP3-T1-F

Documentation / verification / validation /benchmarking (in conjunction with IMP1)

Certifications of the various equilibrium modules.

G. Pereverzev

 

01/01/2006

31/12/2007

 

 

 

 

ITM-05-IMP3-T2-A

Identification of existing non-linear modules (in conjunction with IMP2).

Documentation of pieces of code in existing transport codes that could be turned into ITM  non-linear modules.

V. Parail

 

01/07/2005

31/09/2005

 

 

 

 

ITM-05-IMP3-T2-B

Formation of working groups (in conjunction with IMP2).

Creation of functioning working groups

V. Parail

 

01/08/2005

31/12/2005

 

 

 

 

ITM-05-IMP3-T2-C

Preparation of standardised interfaces (in conjunction with IMP2 and ISIP).

Version 1 of the standard interface for each physics module

V. Parail

 

01/08/2006

31/03/2006

 

 

 

 

ITM-05-IMP3-T2-D

Preparation of non-linear modules by extraction from existing codes (in conjunction with IMP2).

Various non-linear physics modules that could be used by the CPP or by existing transport codes.

V. Parail

 

01/01/2006

31/12/2006

 

 

 

 

ITM-05-IMP3-T2-E

Implementation of prepared non-linear modules (in conjunction with IMP2).

Implementation of modules in CPP or existing transport codes (from the above process or from other IMP’s).

V. Parail

 

01/04/2006

31/12/2007

 

 

 

 

ITM-05-IMP3-T2-F

Documentation / verification / validation /benchmarking (in conjunction with IMP2)

Certifications of the various non-linear modules.

V. Parail

01/01/2006

31/12/2007

 

 

 

 

ITM-05-IMP3-T3-A

Identification of existing transport modules (in conjunction with IMP4).

Documentation of pieces of code in existing transport codes that could be turned into ITM  transport modules.

D. Kalupin

 

01/07/2005

31/09/2005

ready

 

 

 

ITM-05-IMP3-T3-B

Formation of working groups (in conjunction with IMP4).

Creation of functioning working groups

D. Kalupin

 

01/08/2005

31/12/2005

In progress

 

 

 

ITM-05-IMP3-T3-C

Preparation of transport modules by extraction from existing codes.

Various transport physics modules that could be used by the ISIP or by existing transport codes.

D. Kalupin

 

01/08/2006

31/03/2006

Almost done

0.2

P.Strand, D.Kalupin

ITM-05-IMP3-T3-D

Preparation of standardised interfaces (in conjunction with IMP4 and ISIP).

Implementation of modules in ISIP or existing transport codes (from the above process or from other IMP’s).

D. Kalupin

 

01/01/2006

31/12/2006

Almost done

0.2

P.Strand, G.Corrigan, D.Kalupin

ITM-05-IMP3-T3-E

Documentation / verification / validation /benchmarking (in conjunction with IMP4).

Certifications of the various transport modules.

D. Kalupin

 

01/04/2006

31/12/2007

Not ready

1.0 – 2.0

C.Angioni, F.Imbeaux, D.Kalupin, V.Parail, G.Pereverzev, B.Scott, P.Strand

ITM-05-IMP3-T3-F

Implementation of prepared transport modules (in conjunction with IMP4 and ISIP).

Implementation of modules in ISIP or existing transport codes (from the above process or from other IMP’s).

D. Kalupin

01/01/2006

31/12/2007

Not ready

Waits for the code
platform and V&V results

0.2

P.Strand, D.Kalupin

ITM-05-IMP3-T4-A

Identification of existing source modules (in conjunction with IMP5).

Documentation of pieces of code in existing transport codes that could be turned into ITM  source modules.

V. Basiuk

 

01/07/2005

31/09/2005

 

 

 

 

ITM-05-IMP3-T4-B

Formation of working groups(in conjunction with IMP5).

Creation of functioning working groups

V. Basiuk

 

01/08/2005

31/12/2005

 

 

 

 

ITM-05-IMP3-T4-C

Preparation of standardised interfaces(in conjunction with IMP5 and ISIP).

Version 1 of the standard interface for each physics module

V. Basiuk

 

01/08/2006

31/03/2006

 

 

 

 

ITM-05-IMP3-T4-D

Preparation of source modules by extraction from existing codes(in conjunction with IMP5).

Various source physics modules that could be used by the CPP or by existing transport codes.

V. Basiuk

 

01/01/2006

31/12/2006

 

 

 

 

ITM-05-IMP3-T4-E

Implementation of prepared source modules(in conjunction with IMP5).

Implementation of modules in CPP or existing transport codes (from the above process or from other IMP’s).

V. Basiuk

 

01/04/2006

31/12/2007

 

 

 

 

ITM-05-IMP3-T4-F

Documentation / verification / validation /benchmarking(in conjunction with IMP5)

Certifications of the various source modules.

V. Basiuk

 

01/01/2006

31/12/2007

 

 

 

 

ITM-05-IMP3-T5-A

Identification of existing edge-core modules.

Documentation of pieces of code in existing transport codes that could be turned into ITM  edge-core modules.

D. Coster

 

01/07/2005

31/09/2005

Preliminary work completed

0..05

Coster, Bonnin, Wiesen, Corrigan

ITM-05-IMP3-T5-B

Formation of working groups.

Creation of functioning working groups

D. Coster

 

01/08/2005

31/12/2005

Supposed to be tackled by Innsbruck/Ljublana --- held up by funding issues

ITM-05-IMP3-T5-C

Preparation of standardised interfaces (in conjunction with ISIP).

Version 1 of the standard interface for each physics module

D. Coster

 

01/08/2006

31/03/2006

Should be done by 2007-04

ITM-05-IMP3-T5-D

Preparation of edge-core modules by extraction from existing codes.

Various edge-core physics modules that could be used by the CPP or by existing transport codes.

D. Coster

 

01/01/2006

31/12/2006

Not started

ITM-05-IMP3-T5-E

Implementation of prepared edge-core modules.

Implementation of modules in CPP or existing transport codes (from the above process or from other IMP’s).

D. Coster

 

01/04/2006

31/12/2007

Not started

ITM-05-IMP3-T5-F

Documentation / verification / validation /benchmarking

Certifications of the various edge-core modules.

D. Coster

 

01/01/2006

31/12/2007

Not started

ITM-07-IMP3-T1

Whole device modelling

(i) Report outlining existing resources (after 3 months);

(iia) Delivery of the first (simple) tool for Whole Device Modelling (after 9 months)

(iib) Delivery of a more comprehensive tool (or tools) for Whole Device Modelling (after 18 months)

(iii) Report outlining the resources required for the development of more comprehensive tools (after 6 months; i.e. 3 months after Deliverable #1)

(iv) To be determined on the basis of deliverable #3

D. Coster

 

 

 

 

 

 



*  at the level of Project Leader or Deputy Project Leader

**  deadline for task completion, and to initiate the approval procedure by EFDA-CSU.

*** Monitoring comments